The crew and equipment arrived last Thursday 3/3/05 and started moving sand
around. The carpenters and dump trucks arrived Friday and by Saturday
morning the first form was in place on the beach.
We have a set of plans should anyone like to see what's going on and will
post pictures as the work progresses.
March 5th, 2005

March 16th, 2005


March 18th, 2005
All 6 forms are complete and ready for concrete.
A big thanks to the Saboungi construction crew for doing such a great job of
cleaning up for Thunder Mug.

Mid May at the Open House
.jpg)
As of May 25...
Here
is proof of Mounir using tools

North ramp almost done
Just starting the South ramp
South ramp almost done
As of 6/15/05 construction is done except for the removal of some rocks and
trees
July 11, 2005 main construction is done, we are just starting the new roof...
3.jpg)
9.jpg)
2.jpg)
A big thank you to Saboungi Construction, Inc. for the fine job they did.
Mounir Khabazeh, Project Manager and his foreman and workers took extra care
to leave things where we could still do our various events on the weekends even
though is must have cost them time to accommodate us.